MacProject II displays a subproject’s duration as the supertask’s task duration.
When calculating the duration for a supertask, MacProject II converts the working time from the subproject to the proper units for the master project.
-- part contents for background part 27
----- text -----
Subproject Dates & Durations
-- part contents for background part 28
----- text -----
About Units of Duration
-- part contents for background part 7
----- text -----
If the unit of duration in the subproject is different from that of the master project, the supertask’s duration is likely to contain a fractional quantity.